1CorporateConferencePlanningSchedule.mpp
[removed]
592w4.docx
Examine the sample project and interpret your decision points using schedule compression techni
Apr 13, 2025
0 views
This is a sample solution our expert wrote for a client with similar requirements.
1CorporateConferencePlanningSchedule.mpp
[removed]
592w4.docx
Examine the sample project and interpret your decision points using schedule compression techniques, such as resource leveling, fast tracking, overtime, or crashing. In a Word document, answer the following questions.
1. How do you see the schedule health per SV? What would you recommend? (Approximately 200 words, 40 points)
2. How do you see the cost and budget health per CV? What would you recommend? (Approximately 200 words, 40 points)
3. What are the benefits of using indices (SPI/CPI) compared to variances (SV/CV)? (Approximately 100 words, 20 points)
image1.png
592W1.docx
The goal of this Course Project is for you to learn how to create a project management plan in MS Project and how to effectively use the cost and schedule tools in MS Project to successfully manage project costs and schedule.
This Course Project requires the use of Microsoft Project.
Component Deliverable
Tasks
Project Proposal
1. Select a project topic that contains sufficient details to demonstrate your understanding of the course concepts. Here are some ideas for project topics.
· Planning a destination family reunion for 150 people
2. Create the Project Proposal with the information (e.g., concept, timeline, budget, benefits, action request) requested. The Project Proposal Sample document is available in the Project Resources and Naming Conventions section.
3. Submit the Project Proposal in a two-page Word document.
Project Overview Report
1. Using MS Project, create a first-level work breakdown, also known as your to-do list, including your major deliverable milestones and/or your preliminary tasks. They can be summarized in approximately 10 rows or lines. You may also want to indent some of your preliminary tasks, like in the following example. To indent, select the task and then Task>Indent Task. Once you indent, you will see that the preceding task will turn to bold, which is also called a summary task. (This is not a complete WBS; therefore, you do not drill down into the smallest activities with 40+ rows or lines, which will be addressed in Part 2.)
2. Build the reports by navigating to Report>Dashboards>Project Overview.
3. Submit the Project Overview Report either in a MS Project file or as a screenshot.
Stakeholder Communication
1. Draft an email message as a Word document addressed to the project team. Your message should provide a high-level overview of key elements of your selected project topic: objectives, cost, duration, success measurements, and so forth. (This is about briefing your Project Proposal and MS Project work into one page.)
2. Submit an email message in a Word document.
image1.png
592w5.docx
You will be completing the following components of your Course Project Part 4 deliverables. This deliverable is worth 100 points.
1. Earned Value Analysis (20 points)
2. Project Status Communication (20 points)
3. Final Course Project Summary (60 point
Component Deliverable
Tasks
Earned Value Analysis
1. Set the project status date to a date that is halfway through your project.
2. Your project should show the tasks completed as of that date and any cost changes that have occurred. At least 10% of your task should reflect a cost overrun and 5% should come in below budget. You can choose which tasks to modify (10% more, 5% less are approximates). See the following about how to mark task completions. Hover on a task and select Task>Mark on Track (select the drop-down arrow)>Update Tasks.
3. Set the baseline by selecting Project>Set Baseline>Set Baseline>OK>Yes. Then, complete the earned value analysis (EVA) by selecting Reports>Costs>Earned Value Report.
This image is only an example. Results will differ when data is entered.
4. Submit the Earned Value Analysis in either a MS Project file or as a screenshot.
Project Status Communication
1. Interpret the results of the EVA and write a narrative as a project status communication in an MS Word document. The interpretation of the following calculation is required, which also can be automatically produced with Microsoft Project. This is similar to the previous screenshot by selecting View>Tables>More Tables>Earned Value, as an option.
a. Earned Value Over Time: BCWS (Planned Value, PV), BCWP (Earned Value, EV), ACWP (Actual Cost, AC)
b. Variance Over Time (Variance Analysis: SV, CV)
c. Indices Over Time (Performance Index: SPI, CPI)
2. Submit the Project Status Communication with EVA Interpretation in a one-page Word document.
Final Course Project Summary
1. The final Course Project Summary should have the following breakdown.
a. It summarizes the content, as well as the Microsoft Project work, from the entire document with quantifiable highlights, such as overall project cost and schedule performance and estimate to completion, and makes the pitch to project stakeholders to continue the project. This is where you have to act as a project manager and a businessperson. Make sure you utilize references and appendices accordingly. This is worth 25 points.
b. This section includes a forward-looking estimate of the project completion date and the final project costs based on the performance analysis. It proposes appropriate corrective action(s) that should be taken at this point to put the project back on track based on the Earned Value Management (EVM) performance analysis, as necessary. Make sure you utilize references and appendices accordingly. This is worth 25 points.
c. The lessons learned section discusses what you would do differently if you were going to do this kind of project again. This is worth 10 points.
2. Submit the Final Course Project Summary in a two- to three-page Word document.
image1.png
image2.png
image3.png
image4.png
592w2.docx
You will be completing the following components of your Course Project Part 2 deliverables. This deliverable is worth 100 points.
1. Scope Statement (40 points)
2. Detailed Resource Loaded Baseline WBS and Schedule
3. RACI Chart (20 points)
Component Deliverable
Tasks
Scope Statement
1. Create the project scope statement, which is an extended version of your project proposal. It primarily aims to clarify two aspects of the project—setting the acceptance criteria so you can have a smooth closure at the end of the project and rules and regulations to decrease the ambiguity in the team while managing the project. For your convenience, the Project Scope Statement Sample document is available in the Project Resources and Naming Conventions section.
2. Submit the scope statement in a one- to two-page Word document.
Detailed Resource Loaded Baseline WBS and Schedule
1. This is the part to extend the preliminary tasks (approximately 10 lines) you had in Part 1. Using your scope statement, input your work packages into MS Project. The WBS should be created in MS Project, following standard indent and hanging indent practices used in WBS creation. The WBS and schedule must have proper grouping, indenting, and coding for approximately 25 to 40 line items. Review the Project Sample in the Project Resources and Naming Conventions section for an example of a well-developed work breakdown structure
a. Create the WBS column. Hover on the Task Name column and right-click for the drop-down menu so you can select Insert Column, and then type in WBS manually and select the WBS to have your outline numbers.
b. Review your duration. (Hint: Please remember, do not touch the bold task. Manage the content of the bold, also known as summary tasks, because those tasks are aggregated automatically.)
c. Review your predecessors. This is to mimic the conditional tasks we have in real-life. As seen in the following screenshot, if you put the number 4 as a predecessor for line 5, line 5 cannot start before line 4 finishes first.
d. Create the critical path by selecting Gantt Chart Format>Critical Tasks. This is to know which tasks of yours (usually color coded in red bars on the Gantt Chart) are more critical (that means zero free or slack time) so you can be more cautious (with contingency plans) about them.
2. Baseline Resource Plan
a. Define your resources by selecting Resource>Team Planner>Resource Sheet. You do not fill each cell. Some are being used as-is. You may want to work on the blue zone. Also, 100% means one person, 200% means two people, so forth. Once you are done, you may want to go back by selecting on Team Planner>Gantt Chart.
b. Assign your resources task by task. Hover on the task (not summary task, which are the bold ones) and right-click to select Assign Resources. Then review the units. You will see the cost will be populated automatically. Then select Assign or just close the window.
3. Submit the WBS and Schedule in either a MS Project file or as a screenshot.
RACI Chart
1. Develop a RACI chart, responsibility assignment matrix, for the project according to the description in Section 10: Tools and Techniques and illustrated in Figure 10-18 of the
Process Groups: A Practice Guide.
2. Submit the RACI Chart in a Word or Excel document.
image1.png
image2.png
image3.png
PROJ592-W3.docx
Component Deliverable
Tasks
Detailed Resource Loaded Baseline WBS and Schedule
1. This is the part to extend the preliminary tasks (approximately 10 lines) you had in Part 1. Using your scope statement, input your work packages into MS Project. The WBS should be created in MS Project, following standard indent and hanging indent practices used in WBS creation. The WBS and schedule must have proper grouping, indenting, and coding for approximately 25 to 40 line items. Review the Project Sample in the Project Resources and Naming Conventions section for an example of a well-developed work breakdown structure
a. Create the WBS column. Hover on the Task Name column and right-click for the drop-down menu so you can select Insert Column, and then type in WBS manually and select the WBS to have your outline numbers.
b. Review your duration. (Hint: Please remember, do not touch the bold task. Manage the content of the bold, also known as summary tasks, because those tasks are aggregated automatically.)
c. Review your predecessors. This is to mimic the conditional tasks we have in real-life. As seen in the following screenshot, if you put the number 4 as a predecessor for line 5, line 5 cannot start before line 4 finishes first.
d. Create the critical path by selecting Gantt Chart Format>Critical Tasks. This is to know which tasks of yours (usually color coded in red bars on the Gantt Chart) are more critical (that means zero free or slack time) so you can be more cautious (with contingency plans) about them.
2. Baseline Resource Plan
a. Define your resources by selecting Resource>Team Planner>Resource Sheet. You do not fill each cell. Some are being used as-is. You may want to work on the blue zone. Also, 100% means one person, 200% means two people, so forth. Once you are done, you may want to go back by selecting on Team Planner>Gantt Chart.
b. Assign your resources task by task. Hover on the task (not summary task, which are the bold ones) and right-click to select Assign Resources. Then review the units. You will see the cost will be populated automatically. Then select Assign or just close the window.
1. Submit the WBS and Schedule in either a MS Project file or as a screenshot.
Network Diagram
1. Complete your Network Diagram by selecting Task>Gantt Chart>Network Diagram to determine if your project is logically sequenced and to ensure that you have captured your dependencies by linking the appropriate tasks.
1. Submit the Network Diagram in either a MS Project file or as a screenshot.
Preliminary Scope and Budget Balancing
2. Complete a Cost Overview report by selecting Report>Dashboards>Cost Overview.
3. Complete a Resource Overview report by selecting Report>Resources>Resource Review.
4. Discuss how you balance the scope and budget, because the requirements you initially gathered will no doubt exceed your budget and new priorities will have to be set (maximum of two paragraphs).
2. Submit the Preliminary Scope and Budget Balancing in a one-page Word document.
Resource Leveling
1. Using the Overallocated Resources and Resource Overview Reports as a starting point, level your resources so that you can submit an Overallocated Resource Report that shows no overallocated resources. Go to Resources>Level All.
2. Complete the Overallocated Resources reports by selecting Report>Resources>Overallocated Resources.
5. Submit the Overallocated Resource Report in either a MS Project file or as a screenshot.
Balancing Scope and Budget Discussion
1. Discuss how you balance scope and budget. As the requirements you initially gathered will no doubt exceed your budget, new priorities will have to be set. If your resources do not exceed your budget, then discuss what you did when developing your project plan to ensure this result. You may want to conceptually discuss what can be done to improve your project in respect to advanced scheduling techniques, for example, fast tracking, overtime work, or crashing.
3. Submit the Balancing Scope and Budget Discussion in a one-page Word document.
You will be completing the following components of your deliverables. Network Diagram
1. Preliminary Scope and Budget Balancing
2. Resource Leveling
3. Balancing Scope and Budget Discussion
image6.png
image1.png
image2.png
image3.png
image4.png
image5.png
Need a similar assignment?
Our expert writers can help you with your specific requirements. Get started today.